Lithuania, Latvia and Estonia can further expect sufficient funding for the synchronization of their power grids with that of continental Europe, European Commissioner for Energy Union Maros Sevcovic said in Vilnius on Friday.
Sevcovic: EU funding for Baltic synchronization should be sufficient
© DELFI / Valdas Kopūstas

To ensure funding, proper preparations for the second stage involving the laying of a new submarine cable, Harmony Line, between Lithuania and Latvia, have to be made, the European commissioner said.

"The decision which has already been approved that it will be more than 300 million euros just for the first phase. We are already discussing today with the president, prime minister and (Lithuanian Energy Minister – BNS Lithuania) Zygimantas Vaiciunas about the second phase. My only plea was to prepare all the projects on time in an appropriate quality, which I know will be the case. In that case, I'm sure, that Europe will be able to properly fund also the second phase and the 2025 deadline will be met," Sevcovic said during a discussion held in Vilnius on Friday.

He did not go into detail on how much the European Union could further spend on the project but underlined that the synchronization project is a priority for everyone "who deals with energy in Brussels."

Sevcovic also said he has a regular discussion about the synchronization (and also de-synchronization from the post-Soviet BRELL system) with Russian representatives.

"I have regular meetings with him (the Russian energy minister) (...) What I think he said in a repeated manner that they fully respect the decision of the Baltic countries to be connected to the continental Europe network (...) What I think he also hinted at was: after you are synchronized with Europe they wouldn't like to close all bridges, that they would like to have a possibility for trade. I understand that this is politically something which has to be discussed and the parameters have to be evaluated. It's very much in the hands of the Baltic states how you will take it further," the European Commissioner said.

Rimvydas Stilinis, board chairman at Lithuania's power transmission system Litgrid said in late June the Harmony Line project and related infrastructure would require the largest share of investment of the whole project, standing at around 850 million euros, with Poland still calculating its needs.

Lithuania hopes to receive the maximum amount of 75 percent of the total costs, or 637 million euros, under the Connecting Europe Facility, as the EU allocated the same share for the first stage.

In March, the European Commission endorsed funding for the first synchronization stage, giving 323 million euros to the Baltic states, including 125 million euros to Lithuania.

The total synchronization project costs will stand at around 1.5 billion euros, with the EU funding expected to amount to 1.13 billion euros.

The Baltic grids are still part of the post-Soviet BRELL ring, which also includes Russia and Belarus, and remain dependent on the control center in Moscow and the Russian electricity system. The Baltic states want to synchronize with continental Europe by 2025.

BNS
It is prohibited to copy and republish the text of this publication without a written permission from UAB „BNS“.

Car cleaning firm says data of 50,000 customers leaked

Svaros Broliai, a Lithuanian car washing and cleaning services provider, said late on Monday that...

No plans to relaunch Vilnius-Minsk passenger train services

Minsk wants to relaunch passenger train services to Vilnius, halted two years ago due to the...

Lithuania bans Russian gas imports except transit to Kaliningrad

Lithuania has passed a law banning Russian natural gas imports into the country, except for gas...

Key Lithuanian companies protected from Russian, Belarusian control

As Latvia last week banned Russian and Belarusian legal or natural persons from holding stakes in or...

Lithuania and Kazakhstan aim to develop economic ties and transport connections

Lithuania and Kazakhstan seek to increase the volume of bilateral trade through much closer...

Top news

Adviser: extra-NATO forces may temporarily arrive in Lithuania now as well

Additional NATO forces can be temporarily deployed in Lithuania now, if necessary, but permanent...

Simonyte: Lithuania ready to step up expert support to Ukraine

Lithuania is ready to continue and step up its expert support to Ukraine, Prime Minister Ingrida...

Car cleaning firm says data of 50,000 customers leaked

Svaros Broliai, a Lithuanian car washing and cleaning services provider, said late on Monday that...

Bayraktar drone arrives in Lithuania to be handed over to Ukraine

A Bayraktar combat drone has been delivered to Lithuania to be handed over to Ukraine, Defense...

Battle in Klaipeda: Lithuania drops to a good Czech team but the future of LT basketball looks very bright

Ending this window of the World Cup qualification tournament with a win in their match up against a...